Leh, DD, CEC/Chairman, Adv. Tashi Gyalson, chaired a review meeting today to take stock of the ongoing interior construction works of the Assembly Hall at the Council Secretariat.
During the meeting, CEC held a detailed discussion with the concerned officials and stakeholders regarding the pending works and the progress made so far. He further directed that all remaining tasks be completed with proper finishing and ensured within the timeline of mid-October.
Following the meeting, H’CEC carried out a detailed inspection of the Assembly Hall.
He carefully examined the progress in different sections of the building and assessed the quality and pace of the ongoing works.
The meeting was attended by SE PWD Dorjey Gyatso, AEE Construction Division Spalzes Dolma, JE PWD Stanzin Chosdon; Principal Design Consultant Monika Chauhan, Sandeep Gupta, executing contractor from Sristi Enterprises Chandigarh, along with other stakeholders.DD